15
1.
When starting section assembly, clean nipples and
nipple ports.
2.
Coat nipples and nipple ports with Hercules Grrip or
other good sealant. See Figure 9.
3.
Place nipples in ports. Take care to seat them
squarely to prevent cocking. Figure 10.
4.
When pulling sections together with tie rods, insert
tie rods in holes nearest to nipple ports. Move tie rods
to proper location, if necessary, only after sections are
fully pulled together. See insert Figure 11.
5.
Oil or lubricate threads, insert rods in lugs with
washers under nuts and tighten uniformly and
evenly so that sections are pulled parallel as they go
together. When all sections are pulled up, locate tie rods
in alternating pairs of upper and lower holes between
adjacent sections. See Figure 11.
6.
Be sure both ends of completed section assembly are
resting evenly on both ends of base.
7.
Apply furnace cement at joints of sections front, top
and back. Apply furnace cement where sections join
the base. See Figure 12.
8.
Place necessary plugs and control wells in correct
locations. See Figure 31 page 24.
A. Plug all other tappings, leaving air vent in top of
one of end sections, and connect water.
B. Fill boiler with water until it runs out air vent. See
Figure 31 port D page 24.
C. Hydrostatically test boiler in accordance with
applicable codes.
D. Check for leaks before continuing with assembly.
E. Drain and remove unnecessary plugs.
Figure 9
Figure 10
INSTALLATION – ASSEMBLY
Figure 11
Apply non-asbestos furnace cement to joints on all sides of boiler.
Figure 12